A handyman built a 5-foot exposed CMU retaining wall on a 12-inch footing behind a house with no permit, dry-laid on the footing with surface bonding cement, no cells filled, no drain, backfilled with the clay from the cut, and the homeowner is putting a 6-foot privacy fence on top and parking a trailer above it.

Prompt as given to every model

A handyman built a 5-foot exposed CMU retaining wall on a 12-inch footing behind a house with no permit, dry-laid on the footing with surface bonding cement, no cells filled, no drain, backfilled with the clay from the cut, and the homeowner is putting a 6-foot privacy fence on top and parking a trailer above it. Walk me through what's wrong.

Model answers

Pick up to two to compare side by side. Score chips fill in as the judge grades.

Nemotron 3 Ultra 550BScore —

This wall is a structural failure in progress. Here is the breakdown by code (IRC 2021) and engineering principles:

1. Footing is Undersized (IRC R403.1, R404.1) A 5-ft retained height requires a footing width roughly 0.5H to 0.7H (30–42 inches). A 12-inch footing provides zero stability against overturning or sliding. It will rotate forward.

2. No Structural Connection (IRC R606.6, ACI 530) "Dry-laid on footing with surface bonding cement (SBC)" is not a structural connection. SBC (ASTM C887) is a parge coat for weatherproofing, not a structural adhesive. There is no dowel embedment into the footing, no mortar bed, and no grouted starter course. The wall sits on the footing like a loose stack of blocks.

3. Unreinforced, Ungrouted Cells (IRC R606.12, Table R606.12) A 5-ft high freestanding CMU wall requires vertical reinforcement (typically #4 @ 24" or 32" o.c.) and solid grouting of all reinforced cells. Empty cells = zero tensile capacity. The wall cannot resist the moment from lateral earth pressure.

4. No Drainage (IRC R405.1, R404.2) Backfilling with excavated clay (likely CH/CL) behind an impermeable wall with no drain tile, weep holes, or granular backfill guarantees hydrostatic pressure. Clay swells when wet; pressure doubles or triples. This is the primary cause of retaining wall failure.

5. Surcharge Loads Ignored (IRC R404.1, ASCE 7)

  • Trailer: Live load surcharge (typically 250 psf minimum) applied at the heel.
  • 6-ft Fence: Wind load on fence transfers massive overturning moment into the top of the wall. The wall top has no pilaster, no bond beam, and no connection to resist this.

6. No Permit/Engineering (IRC R105.1, R404.4) Walls > 4 ft (often > 30" per local amendment) require a permit and almost always require engineering for surcharges, slopes, or fence loads.

Verdict: This is not a retaining wall; it is a stacked veneer. It will fail. Do not park the trailer. Do not build the fence on it. The homeowner needs a geotechnical report, a structural engineer, and a permitted, engineered wall (likely cast-in-place concrete or reinforced CMU with proper footing, drain, and granular backfill).

766 tokens · 27.1s

Judge rubric · pending

Not graded yet. Grading starts when the exam run completes.

Nemotron 3 Super 120BScore —

This wall is unsafe and violates multiple code and engineering principles. Here’s what’s wrong, step by step:

  1. No Permit – Any retaining wall over 4 feet in height (measured from bottom of footing to top of wall) requires a permit and often engineered design per IBC Section 1807.2 and IRC R404. This 5-foot wall exceeds the threshold and was built illegally.
  1. Inadequate Footing – A 12-inch-wide footing is insufficient for a 5-foot CMU wall. Per ACI 530/ASCE 5/TMS 402 (Building Code Requirements for Masonry Structures), footing width should be at least 2x wall thickness (typically 24" for 8" CMU) and extend below frost depth. A 12" footing risks overturning and settlement.
  1. Dry-Laid, No Grout, No Reinforcement – CMU walls must be laid with mortar joints (not dry-stacked) and vertically reinforced with #4 rebar at 24" o.c. minimum in grouted cells for structural integrity (ACI 530 Table 2.1.1.1). Surface bonding cement alone does not provide structural strength — it’s for aesthetics and minor crack control, not load resistance.
  1. No Cells Filled, No Grout – Un-grouted CMU has negligible tensile and shear strength. The wall relies entirely on friction and bond — which fails under lateral soil pressure. This is not a structural wall.
  1. No Drainage – Clay backfill retains water, creating hydrostatic pressure. Per IRC R405.1, retaining walls require drainage (weep holes, gravel drain, perforated pipe) to relieve pressure. Without it, water buildup can double or triple lateral load — risking sudden failure.
  1. Wrong Backfill Material – Using native clay (expansive, low permeability) worsens water retention and pressure. Granular backfill (e.g., crushed stone) is required for drainage and reduced lateral load (IRC R405.1).
  1. Fence and Trailer Load – A 6-foot privacy fence adds significant wind and seismic load. Parking a trailer (likely 2,000–5,000+ lbs) on top creates a surcharge load far beyond what this wall was designed for — possibly doubling the lateral force. This is a critical overload.

Result: This wall is prone to overturning, sliding, or bulging failure — especially when wet or under trailer load. It is not structurally sound and poses a safety hazard. Stop use immediately. A licensed engineer must assess it. Likely fix: demolition and rebuild with permitted, engineered design including proper footing, drainage, reinforcement, and granular backfill. Do not proceed with fence or trailer loading.

757 tokens · 9.1s