Do not allow arbitrary water addition on site. It alters the water-cement ratio (w/cm), voiding the mix design, reducing strength, and increasing shrinkage/cracking risk.
The Rules (ACI 301 / ASTM C94):
- Pre-Placement Only: Water may be added once upon arrival before any concrete is discharged, only if: The slump is below the specified minimum. The total water added does not exceed the maximum allowable water established by the mix design (held by the producer). The truck drum rotates at mixing speed (12–15 rpm) for minimum 30 revolutions* (or 1 min/yd³) after water addition.
- Documentation: The driver must record gallons added on the delivery ticket. You should note time, slump before/after, and gallons on your pour card.
- Hard "No" If: Concrete has already been placed (even one chute). Adding water would exceed the design w/cm limit. Slump is already at or above the specified max. You are using high-range water reducers (superplasticizers)—adding water negates the admixture and causes segregation.
Better Solutions:
- Order the correct slump (e.g., 5"–7" for pump mixes).
- Use Mid-Range/High-Range Water Reducers dosed at the plant or via onboard system.
- Reject the load if slump is out of spec and cannot be legally corrected. Document rejection on ticket.
Bottom line: If the driver doesn't have the mix design's "water remaining" allowance written on the ticket, he cannot legally add water. Reject the load or call the plant for a chemical adjustment.