Call 811 (Sunshine 811) at least two full business days before you dig.
- Florida Statute 556.105 requires notice no later than 5 p.m. two business days prior to excavation (the day of the call doesn’t count).
- Weekend/holiday days don’t count toward the 48-hour window.
- You’ll receive a ticket number—keep it on site.
Mark your proposed dig area with white paint/flags before locators arrive (APWA color code).
Depth & tolerance:
- Hand-dig or vacuum-excavate within 24 inches of any marked utility (F.S. 556.107).
- Maintain 18-inch minimum separation between your new irrigation mainline and any electric/gas/communication line (Clay County typical spec; verify with local inspector).
Landscape lighting:
- Low-voltage (<30 V) lighting cable is not a “utility” for locate purposes, but do not assume—treat unknown lines as live.
- If you’ll cross an existing electrical service, call for a locate anyway.
Exemptions:
- “Routine maintenance” (e.g., replacing a sprinkler head) doesn’t require a new ticket, but any new trench does.
Penalties:
- Failure to notify: up to $5,000 per violation (F.S. 556.115) plus repair costs.
Bottom line: Call 811 (or use the Sunshine 811 app/portal) by Tuesday 5 p.m. for a Thursday start. Document the ticket, photograph marks, and hand-dig near flags.