No, this is not complete or safe. Here's why:
Critical Issues:
1. CSST Bonding Deficiency (NEC 2020 250.104(B) & 2023 250.104(C))
- The CSST (Corrugated Stainless Steel Tubing) must be bonded with a dedicated #6 AWG conductor (or larger) that runs directly from the CSST to the electrical service equipment or grounding electrode conductor
- Bonding at the meter nipple alone is insufficient - the bonding jumper must connect to the CSST itself, not just the black iron pipe
- This is a lightning strike risk - CSST can rupture from electrical energy if not properly bonded
2. Grounding Electrode System (NEC 250.50, 250.53)
- Two ground rods are required only if the first rod has resistance >25 ohms (NEC 250.53(A)(2))
- The copper water line bonding at the panel is correct (NEC 250.104(A))
Immediate Action Required:
- Install dedicated CSST bonding jumper - #6 AWG minimum from CSST to panel/service equipment
- Verify ground rod spacing - rods must be at least 6 feet apart (NEC 250.53(G))
- Test ground resistance - if first rod is <25 ohms, second rod may not be required
Recommendation:
This requires a licensed electrician to install the proper CSST bonding. The current installation creates a significant fire/explosion hazard during lightning strikes. Do not proceed with final walkthrough until corrected.
Code References: NEC 2020/2023 250.104(B)(C), 250.53(A)(2), 250.53(G)