Yes, there are several issues with this approach:
1. Code Violation - Ceiling Framing (IBC 703.4, R703.4): 1/2" gypsum board installed perpendicular to framing is required for ceiling applications. Running sheets parallel to 24" o.c. trusses creates inadequate support - the board spans 24" unsupported between trusses, exceeding the maximum allowable span for 1/2" board (typically 16" o.c. maximum for ceilings).
2. Safety Hazard: The unsupported 1/2" board will sag and potentially fail under the weight of insulation and people walking on it during spraying. This creates a fall-through hazard.
3. Installation Issues:
- Parallel installation means fewer fasteners per truss (only at sheet ends)
- No intermediate support between trusses
- Board edges may not land on framing consistently
Correct Approach:
- Install 1/2" board perpendicular to trusses
- Use 5/8" Type-X board if spanning 24" o.c. (check local code - some jurisdictions require 5/8" for 24" o.c. ceilings)
- Space fasteners maximum 16" o.c. along edges, 24" o.c. field
- Ensure all sheet edges land on truss members
Immediate Action: Stop work and correct the installation direction before proceeding with insulation and spraying. The current installation will fail inspection and poses safety risks.