Crew is hanging a 12 by 16 deck off a two-story brick house.

Prompt as given to every model

Crew is hanging a 12 by 16 deck off a two-story brick house. They set the 2x10 ledger tight against the brick, ran 3/8 by 4-inch lags every 24 inches through the brick into whatever's behind, no flashing, and are ready to hang joists. What's wrong?

Model answers

Pick up to two to compare side by side. Score chips fill in as the judge grades.

Laguna S 2.1Score —

Major issues:

  1. No flashing — This is the biggest problem. Without flashing above the ledger, water will infiltrate behind the ledger, rot the rim joist/sheathing, and cause structural damage. Install a self-flashing membrane (e.g., Grace Ice & Water Shield or Z-flashing) above the ledger, sealed to the brick with polyurethane caulk.
  1. Lag bolts through brick only — 3/8" x 4" lags may not penetrate far enough into the structure behind. You need to anchor into the rim joist or structural framing. Consider through-bolts (1/2" x 8") with washers, or lag shields/expansion anchors rated for brick and verified framing behind.
  1. No gasket/seal between ledger and brick — Even with flashing, you should use a compressible gasket or sealant (like Vulkem) between the ledger and brick to prevent water migration.
  1. Spacing — 24" o.c. is acceptable for 2x10 joists at 16" span, but verify local code requirements (IRC R502.5.1).

Immediate action: Stop hanging joists. Remove the ledger, install proper flashing, seal the interface, and use adequate anchors into structural framing. If you can’t verify what’s behind the brick, consider surface-mounting the ledger with appropriate masonry anchors rated for the load.

This work likely violates local building codes (IRC R502.5.1, R703.1). A permit and inspection may be required. If unsure about structural anchoring, consult a structural engineer or experienced contractor.

480 tokens · 8.8s

Judge rubric · pending

Not graded yet. Grading starts when the exam run completes.

Nemotron 3 Ultra 550BScore —

Stop work immediately. This ledger connection is structurally unsound and violates multiple code provisions (IRC R507.9).

Critical Failures:

  1. Brick Veneer ≠ Structure: You cannot lag into brick veneer. It is non-structural cladding. The lags must penetrate the rim board/band joist inside the wall cavity (IRC R507.9.1.3). You likely have only 1"–1.5" of brick penetration into air/mortar.
  2. No Flashing: IRC R703.4 & R507.9.1.1 require corrosion-resistant flashing over the ledger and up behind the weather-resistant barrier (WRB). Brick requires a specific "Z-flashing" or counter-flashing detail tucked into a mortar joint (reglet) or behind the WRB. Water will rot the rim board and flood the wall cavity.
  3. Wrong Fastener/Spacing: 3/8" lags are undersized for a 12' joist span (tributary load ~600+ plf). IRC Table R507.9.1.3(1) requires 1/2" diameter bolts or code-listed structural screws (e.g., LedgerLok, SDWS) spaced per the table (typically 12"–16" o.c. for 12' span, depending on fastener type). 24" o.c. is insufficient.
  4. No Washers: Lags/bolts require standard cut washers (IRC R507.9.1.3).

Required Fix (Requires Licensed Pro/Engineering if rim board is damaged):

  1. Remove ledger and lags.
  2. Verify solid rim board (min 1" EWP or 2x lumber) behind brick. If missing/rotten, remediate from interior or via brick removal.
  3. Install self-adhered flashing tape on sheathing/rim board.
  4. Mount ledger with 1/2" HDG bolts or code-listed 1/2" structural screws at code-prescribed spacing (check Table R507.9.1.3(1) for your exact joist span/load). Use washers.
  5. Install Z-flashing over ledger top, tucked min 1" into mortar joint (grind reglet) or sealed behind WRB/lap siding. Seal fastener heads.
  6. Maintain 1/2" gap between ledger and brick for drainage/airflow (IRC R507.9.1.2).

Do not hang joists until this is corrected and inspected.